Message-ID: <26078163.1075840862374.JavaMail.evans@thyme>
Date: Tue, 1 May 2001 11:25:00 -0700 (PDT)
From: dave.nommensen@enron.com
To: louise.kitchen@enron.com, geoff.storey@enron.com, philippe.bibi@enron.com, 
	beth.perlman@enron.com, stephen.stock@enron.com, 
	colleen.sullivan@enron.com
Subject: GTV weekly status update
Cc: zhiyong.wei@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=ANSI_X3.4-1968
Content-Transfer-Encoding: 7bit
Bcc: zhiyong.wei@enron.com
X-From: Dave Nommensen <Dave Nommensen/ENRON@enronXgate@ENRON>
X-To: Louise Kitchen <Louise Kitchen/HOU/ECT@ECT>, Geoff Storey <Geoff Storey/ENRON@enronXgate>, Philippe A Bibi <Philippe A Bibi/ENRON@enronXgate>, Beth Perlman <Beth Perlman/ENRON@enronXgate>, Stephen Stock <Stephen Stock/ENRON@enronXgate>, Colleen Sullivan <Colleen Sullivan/HOU/ECT@ECT>
X-cc: Zhiyong Wei <Zhiyong Wei/ENRON@enronXgate>
X-bcc: 
X-Folder: \ExMerge - Kitchen, Louise\'Americas\IT
X-Origin: KITCHEN-L
X-FileName: louise kitchen 2-7-02.pst

Please find below the GTV project status update for this week. Please see the attached file for the project timeline update in Microsoft Project.

GTV status meeting attendees:  Dave Nommensen, Karima Husain, Francis Lim, Jeremy Wong, Bill Fortney, Nayan Dattani, Russ Severson, Narasim Kasaru, Mike Swaim, Chuck Ames, Jay Krish.

Accomplishments:

?	Incorporating physcial deal positions in TDS:
o	Changes to CPR reader process & its unit testing have been completed.
o	Loading prior-day curves into position manager has been completed.
o	Changes for the view aggregation have been completed (please see the attached project timeline).

?	Single point of deal entry for term deals:
o	Single point of deal entry is in user testing with some minor corrections being made as detected.

?	Gas Daily deals:
o	Changes to PortCalc application to create GDI calc in ERMS are complete and ready for testing.
o	IT development items are in progress and on schedule (please see the attached project timeline).

?	Live feeds for Gas Daily/intra-month curves:
o	Development of live feeds has been completed, tested, user-approved and already in production.

?	Option Grid (phase 2):
o	Conversion from Motif into Powerbuilder is in progress.

?	Gas Daily options:
o	Changes to PortCalc application have been completed; waiting for user acceptance testing.

Plans for the week ending 5/4/01:

?	Continue IT development of Phase I items.
?	Continue IT development of Phase 2 issues.

Issues / Open Items:

?	To be determined:  whether  "group of groups" on Cash Positions must be included in the rollout.
?	To be determined:  whether Cash Total needs to be included in Position Manager rollout (and how).
?	Excluding the above 2 items, rollout to production is planned for mid-May.

 
Thanks, Dave N.